Preprod Gateway upgrade to gCube 4.2

Added by Massimiliano Assante over 8 years ago. Updated over 8 years ago.

Status:
Completed
Priority:
Normal
Start date:
Nov 29, 2016
Due date:
Nov 30, 2016
% Done:

100%

Infrastructure:
Pre-Production
Actions #1

Updated by Massimiliano Assante over 8 years ago

  • Status changed from New to Planned
Actions #2

Updated by Massimiliano Assante over 8 years ago

  • Status changed from Planned to In Progress
  • % Done changed from 0 to 50
Actions #3

Updated by Massimiliano Assante over 8 years ago

https://pre.d4science.org/ is up & running, however only a subset of portlets are available at the moment (social and workspace ones).

Actions #4

Updated by Massimiliano Assante over 8 years ago

  • % Done changed from 50 to 90
Actions #5

Updated by Massimiliano Assante over 8 years ago

  • % Done changed from 90 to 100
Actions #6

Updated by Massimiliano Assante over 8 years ago

  • Status changed from In Progress to Completed