Actions
Task #5713
closedD4Research via the Resource Monitor
Status:
Closed
Priority:
Normal
Assignee:
Category:
System Application
Target version:
Start date:
Nov 10, 2016
Due date:
Nov 11, 2016
% Done:
100%
Estimated time:
Infrastructure:
Pre-Production, Production
Description
Please configure the Resource Monitor accessible at services.d4science.org to enable the new VO named D4Research
Updated by Massimiliano Assante over 8 years ago
- Status changed from New to In Progress
- Infrastructure Pre-Production added
Updated by Massimiliano Assante over 8 years ago
- Status changed from In Progress to Paused
- % Done changed from 0 to 50
The infra monitor for preproduction is ready for supporting the new VO, https://pre.d4science.org/infrastructure-monitor
For production we need to plan first, and restart the portal cluster nodes, we can't do it now.
Updated by Massimiliano Assante over 8 years ago
- Status changed from Paused to Closed
- % Done changed from 50 to 100