Actions
Task #3202
closedadd statistical resources to gcube/preprod VO
Status:
Closed
Priority:
Normal
Assignee:
Category:
Other
Target version:
Start date:
Apr 14, 2016
Due date:
% Done:
100%
Estimated time:
(Total: 0.00 h)
Infrastructure:
Pre-Production
Description
The statistical manager service need a lot of resources for working. All these resources should be added to the /gcube/preprod VO
Updated by Roberto Cirillo about 9 years ago
- Status changed from New to In Progress
Updated by Roberto Cirillo about 9 years ago
- Status changed from In Progress to Paused
Updated by Roberto Cirillo about 9 years ago
- Status changed from Paused to In Progress
I'm going to write a java tool for adding a set of resource from a scope to another one
Updated by Roberto Cirillo about 9 years ago
- % Done changed from 0 to 50
The generic resources with secondary type: "StatisticalManagerAlgorithm" have been correctly added to /gcube/preprod VO
Updated by Roberto Cirillo about 9 years ago
- Status changed from In Progress to Closed
Actions