Task #1790

closed

Provide 2 new MongoDB nodes v 3.0 for preproduction environment

Added by Roberto Cirillo over 9 years ago. Updated almost 7 years ago.

Status:
Rejected
Priority:
Normal
Assignee:
_InfraScience Systems Engineer
Category:
System Application
Target version:
Start date:
Dec 11, 2015
Due date:
% Done:

100%

Estimated time:
Infrastructure:
Pre-Production

Description

A new MongoDB cluster is needed for pre production environment.
These new VMs should have the same HW resources of mongoDB production nodes and a storage of 50 GB under the folder /data.
I guess it is possible to use the same ansible playbook.

The new VMs should be named:

mongo1-pre-d4s.d4science.org 
mongo2-pre-d4s.d4science.org
Actions #1

Updated by Roberto Cirillo over 9 years ago

  • Related to Task #451: New VO creation for preproduction added
Actions #2

Updated by Roberto Cirillo over 9 years ago

If possible, I suggest to keep one member in another data center. @paolo.fabriani@eng.it could we have one of this member deployed @ENG ?
If this configuration works in pre production, we could move also a production member @ENG. In this way we have a more protected data if our main data center fails.
What do you think about it?

Actions #3

Updated by Roberto Cirillo over 9 years ago

  • Related to deleted (Task #451: New VO creation for preproduction)
Actions #5

Updated by Paolo Fabriani over 9 years ago

It makes perfectly sense to me. However, as anticipated during the November meeting in Athens, Eng will not be able to provide new VMs before next January (most likely end of), due to a physical migration of the infrastructure to a different site.

Actions #6

Updated by Roberto Cirillo over 9 years ago

  • Tracker changed from Support to Task
Actions #7

Updated by Andrea Dell'Amico about 8 years ago

  • Status changed from New to In Progress
Actions #8

Updated by Andrea Dell'Amico about 8 years ago

  • Status changed from In Progress to Paused

This is a year old. We can pause it for the time being.

Actions #9

Updated by Pasquale Pagano almost 7 years ago

  • Status changed from Paused to In Progress
Actions #10

Updated by Pasquale Pagano almost 7 years ago

  • Status changed from In Progress to Rejected