Actions
Upgrade #10732
closedUpgrade #10585: D4Science Infrastructure Upgrade to gCube 4.9.0
gCubeApps VO upgrade to gCube 4.9.0
Status:
Completed
Priority:
Normal
Assignee:
Target version:
Start date:
Dec 18, 2017
Due date:
% Done:
100%
Infrastructure:
Production
Updated by Roberto Cirillo over 7 years ago
Hosting Nodes
WHN to upgrade
- (CNR) DONE upgrade all the WHNs under the following clusters:
- (CNR) DONE dataminer-bigdata.d4science.org
- (CNR) DONE dataminer-cluster1.d4science.org
- (CNR) DONE dataminer-cloud1.d4science.org
- (CNR) DONE dataminer.d4science.org
- (CNR) DONE dataminer-prototypes.d4science.org
- (CNR) DONE dataminer-genericworker.d4science.org
- (CNR) DONE dataminer-genericworker-proto.d4science.org
- (CNR) DONE dm-pool-manager-proto.d4science.org
- (CNR) DONE dataminer-proto-ghost.d4science.org
Smartgears services
- upgrade all the services under the following clusters:
- (CNR) DONE dataminer-bigdata.d4science.org
- (CNR) DONE dataminer-cluster1.d4science.org
- (CNR) DONE dataminer-cloud1.d4science.org
- (CNR) DONE dataminer.d4science.org
- (CNR) DONE dataminer-prototypes.d4science.org
- (CNR) DONE dataminer-genericworker.d4science.org
- (CNR) DONE dataminer-genericworker-proto.d4science.org
- (CNR) DONE dm-pool-manager-proto.d4science.org upgrade dm-pool-manager service
- (CNR) DONE dataminer-proto-ghost.d4science.org: update only scopes
Updated by Roberto Cirillo over 7 years ago
- Status changed from Planned to In Progress
Updated by Roberto Cirillo over 7 years ago
- Status changed from In Progress to Completed
- % Done changed from 0 to 100
Actions